How to handle scope creep.
Do not refuse changes. Make each one visible and agreed.
1. Write down the agreed scope
A short list of what is included and what is not. Refer to it when asked for more.
2. Log every request, even small ones
Small asks add up. Record the date and who asked.
3. Check the impact before answering
Estimate time and cost. Tell the client the effect before any work starts.
4. Get written approval
A one-line yes from the client is enough. Keep it with the request.
5. Show the running total
When a client sees twelve small items together, they prioritise on their own.
Tools
A sheet is enough at first. A request tracker with a client portal keeps the log, the approval and the status in one place.
Questions.
What is scope creep?
Work growing beyond what was agreed, usually through many small requests.
How do I say no without losing the client?
Do not say no. Say what it affects, and let them choose.